200 Contractual Problems and their Solutions

200 Contractual Problems and their Solutions

von: J. Roger Knowles

Wiley-Blackwell, 2012

ISBN: 9781118257043 , 480 Seiten

3. Auflage

Format: PDF, ePUB, OL

Kopierschutz: DRM

Windows PC,Mac OSX für alle DRM-fähigen eReader Apple iPad, Android Tablet PC's Apple iPod touch, iPhone und Android Smartphones Online-Lesen für: Windows PC,Mac OSX,Linux

Preis: 95,99 EUR

Mehr zum Inhalt

200 Contractual Problems and their Solutions


 

200 Contractual Problems and their Solutions

3

Contents

5

Foreword

23

Preface

25

Chapter 1: Procurement

27

1.1. What are ‘entire contracts’ and how relevant are they in the construction industry?

27

1.2. Do projects where the parties enter into partnership arrangements require a formal contract to be agreed?

29

1.3. What is the effect of an agreement to undertake work which is expressed as being ‘Subject to Contract’?

31

1.4. What is Two-Stage Tendering and how does it operate?

33

1.5. Where tender enquiry documents indicate that an established...

35

1.6. What liability does a tendering contractor have who in its bid names key personnel...

37

1.7. Can a contract which is freely entered into by the parties not be enforced on the...

39

1.8. Can an architect or engineer be held to have acted negligently for advising a client to...

41

1.9. Where an unsuccessful tenderer is prevented from adjusting its tender after it has been...

44

1.10. What is the difference between Management Contracting and Construction Management?

46

1.11. A public sector project is advertised and tenders invited. Within the advertisement, it is...

48

Chapter 2: Tenders and Bidding

53

2.1. What is meant by the Battle of the Forms?

53

2.2. If a tender which contains an error is accepted in full knowledge of the error, has the tenderer any redress?

55

2.3. Where a contractor or subcontractor submits a tender with its own conditions of contract...

56

2.4. The submission of an unambiguous quotation which receives an unconditional acceptance can...

58

2.5. Where an employer includes with the tender enquiry documents a site survey which proves...

59

2.6. If, after tenders have been received, the employer decides not to proceed with the work...

65

2.7. What is a tender contract and will it assist a contractor/subcontractor who submits...

67

2.8. If an architect/engineer, acting as employer’s agent in a Design and Construct contract...

69

2.9. Does an employer have any liability for not sending a subsoil survey which is in his possession...

70

2.10. If a subcontractor submits a lump sum estimate to a contractor to carry out the subcontract work...

72

2.11. Where a tender enquiry requires tenders to remain open for acceptance for a specific period...

73

Chapter 3: Design

75

3.1. What is the difference between a f?itness for purpose responsibility and an obligation to exercise...

75

3.2. Where a contractor/subcontractor’s drawings are ‘approved’, ‘checked’, ‘inspected’, etc. by...

79

3.3. Who is responsible for co-ordinating design? Can a main contractor be legitimately given this...

82

3.4. Can a contractor be held responsible for a design error where the employer appoints an architect...

83

3.5 Can a main contractor be responsible if a nominated/named subcontractor’s design is defective?

84

3.6. Must a contractor notify an architect/engineer of defects in his design?

86

3.7. Where an architect/engineer includes a new product in his design following advice from a...

88

3.8. Where an architect/engineer is required by the conditions of the contract to approve, or accepts...

89

3.9. Where is the line to be drawn between an architect/engineer’s duty to design the works or a...

90

3.10. Where an item of work has been properly provided for in the Employer’s Requirements but is...

92

3.11. Is the contractor entitled to payment for design in full when the design work has been completed...

94

3.12. On a design and construct project, where the architect is novated from the employer to the contractor...

95

Chapter 4: Letters of Intent

97

4.1. Mr Justice Clarke, in the case of RTS Flexible Systems Ltd v. Molkerei Alios Muller (2010)...

97

4.2. What risk is a contractor taking if it receives a letter of intent which places a cap on expenditure...

99

4.3. When work is undertaken in accordance with a letter of intent without a contract being entered...

101

4.4. Under what circumstances, if any, could a letter of intent be regarded as a concluded contract?

103

4.5. What are the advantages and disadvantages to an employer and contractor in work being...

105

4.6. Could an architect, engineer or project manager be negligent for recommending to an employer...

106

Chapter 5: Programme

109

5.1. Where a contractor submits a programme which is approved or accepted by the architect/engineer...

109

5.2. Is a subcontractor obliged to follow a main contractor’s programme?

110

5.3. Who owns f?loat time in the contractor’s programme, the architect/engineer or the contractor?

112

5.4. What is the effect of making the programme a contract document?

114

Chapter 6: Delays and Delay Analysis

119

6.1. If work is delayed due to two or more competing causes of delay, often referred to as concurrent...

119

6.2. Will a claim for an extension of time and the recovery of loss and expense which does not...

126

6.3. What is meant by a contractor or subcontractor having to ‘use constantly his best endeavours...

133

6.4. What is meant by ‘Time is of the Essence’?

136

6.5. Where delays to completion of the works have occurred and disputes arise as to the appropriate...

138

Chapter 7: Extensions of Time

143

7.1. Does a contractor or subcontractor lose entitlements to extensions of time if he fails to...

143

7.2. What is the Prevention Principle – does it provide a contractor with assistance in avoiding...

148

7.3. Are minutes of site meetings considered by the courts to be adequate notices of delay...

151

7.4. Can an architect/engineer grant an extension of time after the date for completion has passed?

152

7.5. If the architect/engineer issues a variation after the extended completion date but before practical...

154

7.6. When an architect/engineer is considering a contractor’s application for an extension of time...

156

7.7. Where a contractor’s progress is behind programme, will he be entitled to an extension of...

157

7.8. Some standard forms of contract, such as the JCT contracts, provide for extensions of time...

158

Chapter 8: Liquidated/Delay Damages

163

8.1. What is the difference between liquidated damages and a penalty?

163

8.2. If the employer suffers no loss as a result of a contractor’s delay to completion, is he still...

165

8.3. If a delay is caused by the employer for which there is no specific entitlement to an extension...

167

8.4. Are liquidated damages which are calculated using a formula or based upon a percentage...

169

8.5. If the architect or engineer fails to grant an extension of time within a timescale laid down...

170

8.6. If the contractor delays completion but no effective noncompletion certificate is issued by...

172

8.7. Can a subcontractor who f?inishes late have passed down to him liquidated damages f?ixed...

174

8.8. What is meant by ‘time at large’? How does it affect the employer’s entitlement to levy...

176

8.9. Can a contractor challenge the liquidated damages f?igure included in a contract as being a...

178

8.10. If liquidated damages to be enforceable must be a reasonable pre-estimate of loss...

180

8.11. If liquidated damages become unenforceable and hence an entitlement...

182

8.12. Where a contract includes a single liquidated damages amount for failing to complete the...

183

8.13. Is it possible to include in a subcontract an all-embracing sum for liquidated and ascertained...

185

8.14. Are liquidated damages payable in respect of delays which occur after a contractor’s...

187

8.15. What are the problems associated with applying liquidated damages where provision...

188

8.16. Do liquidated damages provide a complete remedy for delays to a contract?

190

Chapter 9: Variations

193

9.1. Where a contractor/subcontractor submits a quotation for extra work which is accepted...

193

9.2. Can a contractor/subcontractor be forced to carry out a variation after practical completion?

195

9.3. Where work is omitted from the contract by way of a variation, can a contractor or subcontractor...

195

9.4. Where work is omitted from a contract and given to another contractor to carry out, is there a...

197

9.5. Where, due to a variation, a contractor has to cancel an order for the supply of material...

199

9.6. How are ‘fair’ rates defined?

201

9.7. When do quantum meruit claims arise and how should they be evaluated?

204

9.8. Can the issue of a variation to the work ever have the effect of creating a separate or replacement contract?

207

Chapter 10: Loss and Expense/Additional Cost

211

10.1. Where a contractor/subcontractor is granted an extension of time, is there an automatic...

211

10.2. Where a contractor/subcontractor successfully levies a claim against an employer for...

212

10.3. Will a contractor or subcontractor substantially prejudice its case for additional...

213

10.4. When a contractor/subcontractor, with regard to a claim for loss and expense or...

215

10.5. With a programme shorter than the contract period, can the...

221

10.6. Where a contractor submits a programme which is accepted or approved, showing...

225

10.7. Is a contractor/subcontractor entitled to recover the cost of preparing a claim?

227

10.8. Will the courts enforce claims for head office overheads based upon the Hudson...

231

10.9. Where a delay to completion for late issue of information has been recognised...

240

10.10. Once it is established that additional payment is due for prolongation...

241

10.11. When ascertaining contractors’ claims on behalf of employers, how should consultants...

243

10.12. Is a contractor/subcontractor entitled to be paid loss of profit as part of his monetary claim?

246

10.13. Is a contractor/subcontractor entitled to be paid acceleration costs as...

247

10.14. Where a written claims notice is required to be submitted within a reasonable time...

250

10.15. What methods of evaluating disruption have been accepted by...

251

10.16. Can a claims consultant be liable for incorrect advice?

255

10.17. If a delay in the early part of a contract caused by the architect/engineer pushes...

256

10.18. Who is responsible for the additional costs and delay resulting from unforeseen...

257

10.19. Where one party to a contract is in breach and the injured party incurs loss...

260

10.20. What is meant in legal terms by the words ‘consequential loss’?

261

10.21. Is it possible to include in a contract a daily or weekly rate which will be paid to...

262

Chapter 11: Payment

265

11.1. Where a contract requires the contractor to give a guaranteed maximum...

265

11.2. Where a subcontract provides for 2.5% cash discount, does this mean...

267

11.3. Under what circumstances are contractors/subcontractors entitled...

270

11.4. Can a contractor force an employer to set aside retention money in a separate bank account?

271

11.5. If an employer becomes insolvent, what liability does the contractor...

274

11.6. Can a contractor/subcontractor legitimately walk off site if payment is not made when due?

277

11.7. Where a contractor undertakes work which he considers should be paid for on...

279

11.8. Can an architect/engineer sign a daywork sheet and then refuse to certify...

280

11.9. Where a contractor/subcontractor includes an unrealistically low rate in the...

281

11.10. Can a debtor enforce acceptance of a lesser sum in full and f?inal settlement?

283

11.11. How can subcontractors avoid ‘pay when paid’ clauses?

286

11.12. Once the value of a contractor/subcontractor’s work has been certified and...

290

11.13. Can a contractor deduct claims for overpayments levied on one contract...

291

11.14. When a contractor completes significantly early, may the architect/engineer...

293

11.15. Where an architect/engineer undercertifies, is the contractor/subcontractor entitled to claim interest?

295

11.16. Can an architect/engineer refuse to include an amount of money in a certificate in...

299

11.17. Can an employer refuse to honour an architect/engineer’s certificate on the...

300

11.18. Where a cheque is issued in respect of construction work undertaken, can it...

303

11.19. Where agreement is reached whereby one party to a construction contract...

304

11.20. Are there any circumstances when a standard form of construction contract...

306

11.21. What is a project bank account and how do the advantages compare with the disadvantages?

310

11.22. What is the difference between set-off and abatement?

312

11.23. Where a contract requires the contractor to provide information for use...

314

11.24. Where a party to a construction contract is due to make a payment to the...

316

11.25. Where payment is made late, is there a legal entitlement to claim interest?

318

11.26. Where, under a JCT contract, an interim payment is due to be made to the...

320

11.27. Architects, engineers and quantity surveyors are often required to provide...

322

11.28. Where money remains unpaid, is the service of a statutory demand and a...

323

11.29. Where a claim is made by a subcontractor against a main contractor...

325

11.30. Can a contractor or subcontractor refuse to commence work until satisfactory...

327

Chapter 12: Practical Completion and Defects

329

12.1. How are practical completion and substantial completion under the JCT and ICE conditions defined?

329

12.2. Where an employer takes possession of a building or engineering facility before all the...

332

12.3. When does practical completion occur under a JCT Standard Form of Building Subcontract?

334

12.4. Where at the end of the defects liability/rectification period/maintenance period...

336

12.5. Is a contractor/subcontractor absolved from any liability if the employer...

338

12.6. Most subcontracts provide for the release of the f?inalbalance of retention only...

340

12.7. Can an employer recover from the contractor the costs involved...

341

12.8. Where a dispute arises between employer and contractor which...

342

12.9. What is the difference between patent defects and latent defects?

343

12.10. Are there any circumstances where a quantity surveyor could be...

347

12.10. Are there any circumstances where a quantity surveyor could be...

347

12.11. Work has been completed and defects in the contractor’s...

349

Chapter 13: Rights and Remedies

351

13.1. Where a contract requires the parties to act in good faith...

351

13.2. What obligation does a contractor, subcontractor or supplier have...

354

13.3. Is there an unfettered power to reject work given...

356

13.4. If an estimate prepared by an engineer or quantity surveyor proves...

358

13.5. When defects come to light after the architect/engineer has issued...

361

13.6. Who is responsible if damage is caused to a subcontractor’s...

365

13.7. How is the term ‘regularly and diligently’, as used in the standard...

367

13.8. Are there any circumstances under which a...

368

13.9. What is a contractor’s liability to the employer for failing...

370

13.10. Do retention of title clauses still protect a supplier or...

372

13.11. Can the signing of time sheets which make reference to standard...

377

13.12. Can suppliers rely upon exclusion clauses in their terms...

378

13.13. What level of supervision must an architect provide on site?

383

13.14. Where a specification includes a named supplier ‘or other...

386

13.15. If a subcontractor is falling behind programme and in danger...

387

13.16. Can parties to a dispute be forced to submit the matter to mediation?

388

13.17. Do contractors, subcontractors, architects or engineers who have...

390

13.18. Parties to a dispute often make offers to settle which are stated to...

392

13.19. Where a contractor takes over work which is part completed...

394

13.20. Where a contract requires a notification to be in writing, sent...

396

13.21. Where an engineer is employed by the employer, is he legally...

398

13.23. What are the legal responsibilities of a project manager?

402

13.24. Are project managers, when performing duties relating to the

404

13.25. Can a quantity surveyor who is employed by the employer be

406

13.26. Can an architect who recommends a contractor...

407

Chapter 14: Adjudication

409

14.1. Will an adjudicator’s decision be enforced by the courts?

409

14.2. Will a court enforce part only of an adjudicator’s award?

410

14.3. When can it be said that a dispute has arisen which gives rise to an...

411

14.4. To comply with the Construction Act 1996 and be subject to...

414

14.5. Can a dispute concerning oral amendments to a construction contract be referred to adjudication?

417

14.6. Where a mediator is appointed in relation to a dispute in...

418

14.7. Will a court enforce an adjudicator’s award which is clearly wrong?

419

14.8. If a dispute is the subject of ongoing litigation, can one...

421

14.9. Can an adjudicator withhold a decision from the parties until his fees are paid?

422

14.10. If an adjudicator issues a decision late, can it be enforced?

424

14.11. The Construction Act states that ‘a party to a construction...

426

14.12. Where a compromise agreement relating to a dispute...

427

14.13. A matter in dispute can only be referred to adjudication...

428

14.14. Will a clause in a construction contract which states that all...

431

14.15. Are the parties entitled to challenge an adjudicator’s fees on the grounds that they are unreasonably high?

431

14.16. Does a draft adjudicator’s decision constitute a f?inal decision?

432

14.17. Does an adjudicator who communicates with one party without...

433

14.18. Can an adjudicator employ the services of an expert to assist in making a decision?

434

14.19. Where an adjudicator seeks legal advice to assist him in reaching a...

436

14.20. Have the courts laid down any general guidelines as to how...

436

14.21. Where an adjudicator issues a decision involving the payment...

439

14.22. Where an adjudicator’s decision provides for a sum of money...

440

14.23. Can a party to a construction contract who is reluctant to have...

441

14.24. Can the party that is successful in adjudication recover its costs from the losing party?

442

14.25. Where a contractor includes in its subcontract terms a clause...

444

14.26. It has been argued that adjudication in accordance with the...

446

14.27. Where one party claims that the adjudicator has no jurisdiction...

449

14.28. What happens if the adjudication provisions as set out in the...

450

14.29. Is it possible for a Referring Party to restrict or exclude part of the...

452

14.30. Can a losing party refuse to comply with an adjudicator’s decision on the grounds that the Referral Notice was served late?

454

14.31. Section 105(1) of the Housing Grants, Construction and...

456

Table of Cases

459

Index

471