A Practical Guide to the NEC3 Engineering and Construction Contract

A Practical Guide to the NEC3 Engineering and Construction Contract

von: Michael Rowlinson

Wiley-Blackwell, 2011

ISBN: 9781444340174 , 321 Seiten

Format: PDF, ePUB, OL

Kopierschutz: DRM

Windows PC,Mac OSX für alle DRM-fähigen eReader Apple iPad, Android Tablet PC's Apple iPod touch, iPhone und Android Smartphones Online-Lesen für: Windows PC,Mac OSX,Linux

Preis: 89,99 EUR

Mehr zum Inhalt

A Practical Guide to the NEC3 Engineering and Construction Contract


 

A Practical Guide to the NEC3 Engineering and Construction Contract

5

Contents

7

1 Introduction

13

1.1 General

13

1.2 Mechanics not law

14

1.3 A simple formula for understanding a contract

14

1.4 Mandatory or discretionary

15

1.5 Conditions precedent

16

1.6 Note on use of upper case in key words and phrases

16

2 Background to the NECECC

17

2.1 The background: First edition

17

2.2 The second edition

18

2.3 The third edition

19

2.4 Endorsement of NEC3 by the Office of Government Commerce

19

2.5 General philosophy: Aims and objectives

20

2.6 Flexibility

20

2.7 Clarity and simplicity

21

2.8 Stimulus to good management

21

2.9 Other characteristics

22

3 The Options: An Overview

25

3.1 General arrangement of the ECC

25

3.2 Other documents referred to

27

3.3 Contract Data

28

3.4 The published documents

28

3.5 Main Options: General outline

29

4 ‘Spirit of Mutual Trust and Cooperation’

31

4.1 Introduction

31

4.2 Core clause 10.1

31

4.3 What does it mean?

33

4.4 Practical issues

34

5 The Cast of Characters

37

5.1 Introduction

37

5.2 The Employer

37

5.3 The Project Manager

39

5.4 The Supervisor

41

5.5 The Contractor

42

5.6 The Adjudicator

43

5.7 Subcontractors

44

5.8 ‘Others’

44

5.9 Designers

45

5.10 CDM Coordinator

46

5.11 Principal Contractor

46

5.12 Practical issues

47

6 Communications, Early Warnings and other General Matters

49

6.1 Introduction

49

6.2 Communications: The clause

49

6.3 Communications: Practical issues

50

6.4 Early warnings: The clause

52

6.5 Early warnings: Practical issues

54

6.6 Other matters: The clauses

56

6.7 Other matters: Practical issues

59

7 The Contractor’s Main Responsibilities

61

7.1 Introduction

61

7.2 Providing the Works

61

7.3 Contractor’s design

63

7.4 Other matters

64

7.5 Practical issues

67

8 Subcontracting

71

8.1 Introduction

71

8.2 Definition of a Subcontractor

71

8.3 The core clauses

72

8.4 Provisions in the Main Options

73

8.5 Practical issues

73

8.6 Options for forms of subcontract in the NEC3 family

74

9 Testing and Defects

77

9.1 Introduction

77

9.2 Tests and inspections

77

9.3 What is a Defect?

79

9.4 The Defect procedure

80

9.5 The Defects Certificate

82

9.6 Uncorrected Defects

82

9.7 Practical issues

83

10 Title

85

10.1 Introduction

85

10.2 The core clauses

85

10.3 Practical issues

86

11 Risks and Insurance

89

11.1 Introduction

89

11.2 The core clauses

89

11.3 Practical issues

92

12 Time

97

12.1 Introduction

97

12.2 The programme: Contents

98

12.3 The programme: Submitting, accepting and revising

103

12.4 The programme: Practical issues

105

12.5 Starting and finishing

114

12.6 Other matters

117

12.7 Secondary Options related to Time

120

12.8 Practical issues

122

13 Payment

125

13.1 Introduction

125

13.2 The payment process

125

13.3 Payments in multiple currencies

128

13.4 The amount due and the Price for Work Done to Date

128

13.5 Supporting documents and records

138

13.6 The Contractor’s share

141

13.7 The Contractor’s share: Practical issues

143

13.8 Special provisions for the UK

144

13.9 Related Secondary Options

146

13.10 Practical issues

148

14 The Schedules of Cost Components

151

14.1 Introduction

151

14.2 The Schedule of Cost Components

151

14.3 The Shorter Schedule of Cost Components

156

14.4 Application to Subcontractors

157

14.5 Practical issues

158

15 Compensation Events: Theory and Events

163

15.1 Introduction

163

15.2 The theory

163

15.3 The events

165

15.4 Practical issues

180

16 Compensation Events: Procedures

183

16.1 Introduction

183

16.2 Notification by the Project Manager

184

16.3 Notification by the Contractor and the Project Manager’s reply

187

16.4 Other matters associated with notifying compensation events

190

16.5 Quotations: Substance

192

16.6 Quotations: Submission and reply

194

16.7 Assessments by the Project Manager

198

16.8 Implementing compensation events

200

16.9 Practical issues

201

17 Compensation Events: Assessment

207

17.1 Introduction

207

17.2 Changes to the Prices

208

17.3 Changes to the Completion Date and any Key Dates

212

17.4 Project Manager’s assumptions

215

17.5 Other related matters

216

17.6 Practical issues

218

18 Termination

221

18.1 Introduction

221

18.2 Reasons for termination

221

18.3 Implementing termination

225

18.4 Procedures after termination

226

18.5 Assessing the amount due after termination

227

18.6 Practical issues

229

19 Dispute Resolution

231

19.1 Introduction

231

19.2 Option W1

232

19.3 Option W2

235

19.4 Practical issues

240

20 Secondary Options

243

20.1 Introduction

243

20.2 X2: Changes in the law

243

20.3 X4: Parent company guarantee

244

20.4 X12: Partnering

244

20.5 X13: Performance bond

249

20.6 X17: Low performance damages

250

20.7 X18: Limitation of liability

250

20.8 X20: Key Performance Indicators

251

20.9 Y(UK)3: The Contracts (Rights of Third Parties) Act 1999

252

20.10 Z: Additional conditions of contract

252

20.11 Practical issues

253

21 Completing the Contract Data

255

21.1 Introduction

255

21.2 Purpose and form of the Contract Data

255

21.3 Part One: Data for the core clauses

256

21.4 Part One: Data for the Main Option clauses

260

21.5 Part One: Data for the Secondary Option clauses

261

21.6 Part Two: Data for the core clauses

264

21.7 Part Two: Data for the optional statements

265

21.8 Part Two: Data for Main Options A or B

267

21.9 Part Two: Data for Main Options C, D or E

268

21.10 Practical issues

269

22 The Supporting Documents: Need and Content

273

22.1 Introduction

273

22.2 Works Information

273

22.3 Site Information

282

22.4 Practical issues

283

Bibliography

285

Appendix 1 Tables of Clause Numbers, Case Law and Statutes

287

Appendix 2 Tables of Employer’s, Project Manager’s, Supervisor’s, Contractor’s and Adjudicator’s Actions

297